Government Contracts Monitor
Here We Go Again…Possible Federal Government Shut-Down - Actions to Take Now (Updated)
September 27, 2013
Once again we find ourselves faced with a possible federal government shut-down. Contractors need to start planning and communicating now with their respective government contracting officers about how to address the shut-down, possibly as early as this coming weekend or in a couple of weeks. If there is a shut-down, virtually all federal government contractors face serious impacts. Action now will enable contractors to respond appropriately in the event of a shut-down, and to minimize adverse impacts to government programs, control non-reimbursable costs and mitigate, document and account for shut-down costs for which the government will be liable.
Recommended Actions: Every government contractor should take the following steps now:
- Review and determine the impact of a shut-down on each individual contract and pending contract actions;
- Communicate with the cognizant contracting officer on each contract about a shut-down’s effects and the actions to be taken, including, as to ongoing contracts, access to government facilities, personnel and information (including classified information), and how to obtain any needed government approvals, authorizations (including for payment) and directions, or obtain inspection and acceptance of goods being delivered;
- Avoid volunteering or agreeing to continue work under shut-down contracts that will not be compensable;
- Determine the impact on employees and how best to respond, including whether to reassign, otherwise engage (e.g., training), put on paid vacation leave or furlough such employees, and timely communicate the same to the employees (special problems may arise and need to be decided in the case of employees overseas or operating at a distance from their “home” base);
- Notify (in writing) and coordinate with any teaming partners and affected subcontractors and suppliers immediately upon receipt of any actual or constructive “stop work” order, and ensure that each is aware of its flow-down duties and responsibilities, including the duties to mitigate, and to separately document and account for, all shut-down related costs;
- Set-up separate cost accounts for shut-down costs for each affected contract, and ensure that all cognizant personnel fully document and account for all associated costs;
- Identify and take all reasonable steps to mitigate shut-down related costs, and document all decisions; coordinate such actions, where necessary, with the cognizant contracting officer in an effort to get him/her to buy into, or at least be aware of, your cost mitigation efforts and decisions; and
- Timely submit and claim reimbursement for all reasonably incurred shut-down costs.
In addition, contractors should assess the impact of a shut-down on non-contract deadlines. Contractors also may want to assess their ability and plans to continue other business operations in view of delays in government payments in the event of a shut-down.
Background: No money can be paid from the Treasury except pursuant to Congressionally-passed funding authorizations. Federal officials cannot obligate funds before an appropriations measure has been enacted, and cannot accept voluntary services. However, contracting officers are authorized to incur costs necessary to shut-down operations.
This means that contractors cannot rely upon oral or even written assurances, and should not “volunteer,” with the expectation of being paid later. While government employees have been paid retroactively in connection with past shut-downs, the same cannot be said as to contractor employees. Contractors therefore need to protect themselves.
Current Status: If a continuing resolution is not timely passed, the federal government will shut-down effective October 1, 2013. While there are reports that an interim two-month continuing resolution may be agreed to this weekend, the same situation may again arise if a longer-term resolution is not timely reached. If no extension is agreed, there will be a lapse in funding and the government will shut-down.
Legal Parameters: If there is a shut-down, all contracts dependent upon continuing funding will be shut-down, with only limited exceptions for activities determined necessary to save lives or protect property. Contracts already fully funded will not be affected, nor will those few contracts otherwise authorized by law to continue notwithstanding a shut-down.
Ideally each contracting officer would issue a “stop work” order for each affected contract, directing each contractor specifically as to what to do on such contract. However, it is more likely that contracting officers will issue broad guidance memos affecting multiple contracts, under which each affected contract will be subject to a “stop work” order. Upon receipt of notice, each affected contractor will be obligated to shut-down operations as directed, and mitigate the government’s shut-down costs exposure. Contractors will be entitled to recover reasonable and necessary shut-down costs. However, contractors will need to carefully document and separately account for such costs, and timely submit appropriately documented claims to recover them. Re-start costs will need to be tracked separately, and should be negotiated at the time of re-start. “Volunteered” interim activities will not be reimbursed; and any promises or agreements to compensate interim activities likely will not be honored as being outside the authority of any involved government official.
During any shut-down contracting officers will be barred from making new awards, issuing new task orders under ID/IQ contracts, entering into contract amendments or modifications and exercising contract options, which depend on current year funding. Note that other government deadlines, such as for option exercises, proposal submission, claims and agency appeals, bid protests and court filings, will not necessarily be stayed by a shut-down, and contractors will need to assess carefully their obligations in each such instance.
Conclusion: If a shut-down occurs, such will have far-reaching consequences for all government contractors, going to the very heart of their business operations. Contractors need to be prepared and take appropriate actions to minimize their costs and the adverse business impacts of a shut-down. The key is careful planning and timely and regular communication with all involved, particularly the relevant government contracting officers
Editor’s Note: After we posted this article, the FederalGovernment shut-down became a reality. These tips are important to keepin mind but may prove more difficult to implement now that many contractingofficers and other agency personnel are furloughed. However, keep thisarticle in your back pocket because, unfortunately, this may not be the lasttime we’re faced with this same situation.
Hopewell Darneille is the attorney responsible for the content of this article.