Oil and Gas Update
FERC Sidesteps New York’s Denial of CWA §401 Certification Giving Go-Ahead to Millennium Pipeline Company Spur
October 10, 2017
By: Kevin M. McGuire
For any company desiring to construct a natural gas pipeline, all roads lead to FERC. Millennium Pipeline Company, L.L.C. v. Seggos, 860 F.3d 696, 698 (D.C. Cir. 2017).
In a significant and already controversial decision issued in mid-September, the Federal Energy Regulatory Commission (FERC) granted approval for Millennium Pipeline Company L.L.C. (Millennium) to proceed with a pipeline extension project despite the prior denial of the companys application for a Clean Water Act (CWA) §401 water-quality certification by the New York Department of Environmental Conservation (NYDEC). See Millennium Pipeline Company, L.L.C., 160 FERC ¶ 61,065 (September 15, 2017).
As noted in prior articles of August 11, 2016 and September 7, 2017, the Natural Gas Act of 1938 (NGA) vests FERC with exclusive jurisdiction to regulate sales and transportation of natural gas in interstate commerce, including the construction and operation of pipelines. Prior to commencing construction, the NGA requires that the pipeline company obtain from FERC a certificate of public convenience and necessity. Armed with a certificate of public convenience and necessity, the pipeline company may exercise the right of eminent domain to gain property access and construct pipelines. Moreover, even though pipeline construction and operation must comply with environmental laws, the NGA restricts the rights of third parties to use state administrative remedies to challenge pipeline development.
For example, the NGA was amended in 2005 to grant exclusive jurisdiction to the Federal circuit courts of appeal for judicial review of determinations made by state agencies acting pursuant to Federal law on approvals required under Federal law with respect to applicable gas infrastructure. See 15 U.S.C. § 717r (d)(1). Challenges to FERC certificates must be filed either in the D.C. Circuit or in the circuit where the natural gas company is located or does business, where FERC is afforded deference in this decision making process. See 15 U.S.C. § 717r (b).
Before FERC can issue a certificate of public convenience and necessity, FERC must ensure that the proposed pipeline complies with all applicable federal, state, and local regulations. See 15 U.S.C. §717(b)(d); 18 C.F.R. § 4.38. Opponents of pipeline development often use the CWA § 401 certification process to delay or defeat pipeline projects. Section 401 of the CWA requires applicants for federal licenses or permits which may result in a discharge to the waters of the United States to obtain a certificate from the states in which the discharges will occur that the discharges will comply with state-issued water quality standards. See 33 U.S.C. § 1341(a).
On November 13, 2015, Millennium applied to FERC for a certificate of public convenience and necessity requesting authorization to construct a 7.8 mile pipeline spur to provide services to the Valley Energy Center in Wawayanda, New York. On November 9, 2016, FERC issued a provisional certificate of public convenience and necessity for the proposed project. FERC, however, conditioned its approval on proof of Millenniums receipt of all authorizations required under federal law, including the CWA. Because Millenniums proposed pipeline would traverse several streams in New York, the CWA required that New Yorks NYDEC certify that any impacts from the pipeline will comply with the state-issued water quality standards. See 33 U.S.C. § 1341(a)(1).
On November 23, 2015, concurrent with its FERC filings, Millennium applied to NYDEC for CWA § 401 certification. After FERC issued its November 9, 2016 provisional certificate of necessity, NYDEC informed Millennium that regardless of any action by FERC, including the issuance of a Certificate of Public Convenience and Necessity , no construction activities may commence unless the [CWA § 401] application is approved and [NYDEC] issues a [certification].
In December 2016, more than a year after applying to the NYDEC for CWA § 401 certification, Millennium petitioned the D.C. Circuit under § 19(d)(2) of the NGA alleging that NYDEC had unlawfully delayed action on the water quality certification and waived its authority under CWA § 401. The D.C. Circuit dismissed Millenniums petition on jurisdictional grounds, finding that Millennium had not been damaged in light of its other remedies. Millennium, 860 F.3d 696, 698 (D.C. Cir. 2017).
On July 21, 2017, Millennium requested permission from FERC to proceed with construction of the Valley Lateral Project pursuant to the previously-issued provisional certificate of necessity. In its request, Millennium asserted that NYDEC had waived its authority to issue a CWA § 401 certification by failing to act within one year of November 23, 2015, the date of Millenniums application. NYDEC disagreed, contending that the time to act on the application had not been waived since the time did not start to run until NYDEC received a complete application, which it contended was August 31, 2016.
On August 30, 2017, NYDEC denied Millenniums CWA § 401 water certification application. In support of its denial, NYDEC found that FERCs review of the 7.8 mile pipeline spur failed to consider the indirect effects of downstream emissions that would come from the power plant if the connecting pipeline was approved.
Subsequently, on September 15, 2017, FERC rejected NYDECs denial of the CWA § 401 water quality certification for Millenniums pipeline project, finding that the NYDEC had waived its authority to act on the application by failing to do so within the one-year statutory deadline. Citing the plain meaning of the statute, FERC found that state agency had waived its right to review Millenniums application for a water quality certification under CWA § 401. See Millennium Pipeline Company, L.L.C., 160 FERC ¶ 61,065, at 5 (September 15, 2017).
Addressing what it called the crux of the casethe event that triggered the one-year waiver periodFERC looked to the language of CWA § 401 providing that [i]f the State fails or refuses to act on a request for certification within a reasonable period of time (which shall not exceed one year) after receipt of such request, the certification requirements of [Section 401] shall be waived with respect to such Federal application. See Millennium Pipeline Company, L.L.C., 160 FERC ¶ 61,065, at 2 (September 15, 2017) citing 33 U.S.C. 1341(a)(1) (emphasis in original). FERC concluded that receipt was the triggering event and, after consulting the dictionary definition, concluded that the plain meaning of after receipt of the request is the day the agency received a certification application, as opposed to when the agency considers the application to be complete. See Millennium Pipeline Company, L.L.C., 160 FERC ¶ 61,065, at 5 (September 15, 2017).
FERC found that its decision was consistent with Congresss intent and FERC precedent. Congress has explained that the review period of one year was established to ensure that sheer inactivity by the State will not frustrate the federal application. See Millennium Pipeline Company, L.L.C., 160 FERC ¶ 61,065, at 6 (September 15, 2017). Similarly, in Georgia Strait Crossing Pipeline LP, 107 FERC ¶61, 065 (2004), FERC found that the Washington Department of Ecology had waived its CWA § 401 authority after it declined the pipelines certification request more than two years after receipt. See also AES Sparrows Point LNG, LLC 126 FERC ¶ 61,019 (2009) (Order Issuing Certificate).
FERC found further support in its hydropower regulations and case law, as well as D.C. Circuit precedent. As explained by the D.C. Circuit, [i]n imposing a one-year time limit on States to act, Congress plainly intended to limit the amount of time that a State could delay a federal licensing proceeding without making a decision on the certification request. This is clear from the plain text. See Millennium Pipeline Company, L.L.C., 160 FERC ¶ 61,065, at 5 (September 15, 2017) citing Alcoa Power Generating Inc. v. FERC, 643 F.3d 963, 972 (D.C. Cir. 2011). In the final analysis, FERC concluded that, consistent with its precedent in both NGA cases and hydroelectric licensing proceedings under the Federal Power Act, the triggering date for waiver under § 401 of the CWA is the date the certifying agency receives the application.
Although NYDEC may appeal to the D.C. Circuit, that Court may have already foreshadowed its decision. As noted above, Millennium previously petitioned the D.C. Circuit to compel the NYDEC to approve Millenniums application for the CWA § 401 water quality certificate. The D.C. Circuit rejected Millenniums petition because the delay of the NYDEC had not caused injury in fact to Millennium. In reaching its finding of no injury, however, the D.C. Circuit paved the way for Millennium to ultimately receive the sought-after FERC approval:
if the [NYDEC] has delayed for more than a yearas Millennium allegesthe delay cannot injure Millennium. Instead, the delay triggers the Acts waiver provision, and Millennium then can present evidence of waiver directly to FERC to obtain the agencys go-ahead to begin construction.
Millennium Pipeline Company, L.L.C. v. Seggos, 850 F.3d 696, 700 (D.C. Cir. 2017).
This article was authored by Kevin M. McGuire.